The Ground Floor Shop and Café were handed back to MOSI earlier this week for cleaning and stocking, whilst on the Second Floor, carpet has been fitted and the respective fit-out teams have moved into the Conferencing and Banqueting areas to put the final touches to our inspiring new meeting facilities.
Elsewhere, the new entrance area is also nearing completion. New automatic doors have been installed, tested and commissioned and the entrance paving has also been replaced, giving a much more spacious look to the Museum entrance.